Minnesota Department of Transportation

511 Travel Info

Highway 5/East 7th Street and Highway 61/Arcade Street

St. Paul and Maplewood

Join us for Office Hours on Thu, May 1. Community members are invited to stop by to ask questions about the East 7th St. and Arcade St. project. For more information, visit the meetings webpage.

This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.

Traffic impacts

East 7th Street and Arcade Street in Saint Paul and Maplewood project location map

East 7th St. and Arcade St. project area map

View full-size map

All traffic impacts are tentative and weather dependent. Local access to residences and businesses will be maintained. Access and parking for businesses are available using side streets. Intermittent parking may be available on Arcade St. between Wheelock Pkwy. and Maryland Ave. and Magnolia Ave. and York Ave. depending on specific work being done.

Current

Road closures

March 31 through early summer

Upcoming

Information about upcoming traffic impacts will be posted as details become available. Motorists can expect intermittent intersection closures throughout the project area; however, no two consecutive intersections will be closed at the same time. Pedestrians can expect sidewalks and boulevards to be removed and repaved during the project.

Road closures

Summer through early fall
  • Arcade St. is closed to through traffic in both directions between Wheelock Pkwy. and Maryland Ave.

Construction timeline

Arcade Street in Saint Paul and Maplewood construction timeline map

Arcade St. construction timeline map

View full-size map

  • Spring through fall 2025: Arcade St. from East 7th St. to Roselawn Ave.
    • Stage 1A (Arcade St. from Frost Ave. to Wheelock Pkwy.): Late March through early summer
    • Stage 1B (Arcade St. from Wheelock Pkwy. to Maryland Ave. East): Late May through late summer
    • Stage 2A (Arcade St. from Maryland Ave. East to Magnolia Ave. East): Late March through mid-summer
    • Stage 2B (Arcade St. from Magnolia Ave. East to Case Ave. East): Mid-summer through early fall
    • Stage 2C (Arcade St. from Case Ave. East to Neid Ln.): Early fall through late fall
  • Spring through fall 2026: East 7th St. from I-94 to Minnehaha Ave.

Construction activities

Utility work (water, electrical, gas, etc.) will occur intermittently throughout all parts of the project area, not just where road construction is happening.

Arcade St. from Frost Ave. to Wheelock Pkwy.

Ongoing activities:
  • Crews continue to grade sidewalks and curbs through early May
  • Crews continue stormwater sewer installations through early May
  • Crews continue watermain replacement
Upcoming activities:
  • Starting in early May, crews will pour concrete for new sidewalks on the west side of Arcade St. and pour concrete at the Arcade St. and East Wheelock Pkwy. intersection.

Arcade St. from Maryland Ave. to York Ave.

Ongoing activities:
  • Crews continue removing asphalt and grading the roadway between Maryland Ave. and Magnolia Ave. through early June
  • Crews continue utility work through early summer
Upcoming activities:
  • Starting in early May, crews will begin watermain replacement

About this project

In March 2025, we began the two-year reconstruction project along East 7th St., and Arcade St. between I-94 in St. Paul and Roselawn Ave. in Maplewood. When complete, the new roadway will improve traffic flow, decrease traffic delays and improve safety on the road. Construction is expected to be completed in fall 2026.

Summary of work

  • Resurfacing the road
  • Repairing sidewalks
  • Updating sidewalk curb ramps and driveways
  • Updating and improving pedestrian lighting
  • Updating and improving traffic signals
  • Updating and improving bus stops