Reconstruct, improve 
	  2026-2027 roadwork 
	  MnDOT will reconstruct and improve Hwy 95 from Fern St. to Fillmore St. in Cambridge. Project will be done in three work segments with detours in Cambridge.  
	  Current impacts 
	  Prep work fall 2025 - spring 2026 
      Crews will be out preparing for the future construction project, includes: relocating utilities, removing structures and trees/brush, surveying, etc. 
      
        Expect periodic lane, shoulder or sidewalk closures along Hwy 95 
       
	  Hwy 95 project located in Cambridge. Select PNG image to enlarge map Summary of work 
	  
        Expand the four-lane segment from Fillmore St. to Ashland St., includes sidewalks and adjacent entrances  
        Reconstruct from Fern St. to Ashland St., includes  sidewalks and adjacent entrances 
        Replace underground storm sewer and utilities 
        Upgrade signal systems, overhead streetlights and install fiber optic cable  
        Reconstruct the BNSF railway crossing	 
        Visual maps of completed improvements (May 2023): 
          
         
       
	 
	
	  Hwy 95 will be constructed in three segments over two construction seasons in 2026-2027. The project begins on the west end and moves eastward.	  
	  Local access  will be open and maintained along each closed segment by using adjacent side streets, second entrances, temporary driveways or alleys. Pedestrian access will also change; follow detour signs. 
	  Work segments map. Select (PNG) image to enlarge. Schedule at a glance 
	  Table: Tentative work, schedule and detour plans. 
	  
	    
	      
	        Map color When Work segment Detour plans in Cambridge  
	      
	        Purple 
	          
Spring - summer 2026 
	        Fern to Dellwood 
            Close and reconstruct Hwy 95 from west of Fern St., near Rum River, to east of Dellwood St.
	          
	            Westbound Hwy 95 detour via Cypress St. S to Second Ave. SW to Co. Rd. 70 
	            Eastbound Hwy 95 detour from Co. Rd. 70 via Second Ave. SW and Birch St. S 
	            Local access maintained; follow signs along side streets  
	            Hwy 95 Fern to Dellwood detour plan map  (PNG)  
           
	      
	        Blue 
Summer - fall 2026
Dellwood to Main 
            Close and reconstruct Hwy 95 from east of Dellwood St. to west of Main St.
	           
           
	      
	        Orange 
Spring - fall 2027
            
Main to Fillmore 
	          Close and reconstruct Hwy 95 from west of Main St. to east of Fillmore St.
	           
 
         
      
	  Construction plans are tentative and subject to change. More details available once a contractor is on board.