I-35W

Burnsville

This webpage is not updated over the weekend/overnight. For up-to-date information on traffic impacts, visit 511mn.org.

Traffic impacts

I-35W between Cliff Road and the I-35/35W/35E split in Burnsville project location map

I-35W in Burnsville project location map.

View full-size map

All traffic impacts are tentative and weather dependent.

Current

Road closures

9 p.m. Fri, April 25 through October 2026

Bridge closures

5 a.m. Wed, April 16 through 11 p.m. Fri, Nov. 14

Lane closures

9 a.m. Wed, April 16 through 11 p.m. Fri, Nov. 7
  • Hwy 13 is reduced to one lane in both directions with head-to-head traffic over I-35W
Through 11 p.m. Fri, Nov. 14
  • I-35W is reduced to two lanes in both directions between the Burnsville Pkwy. and the I-35/I-35E/I-35W split

Ramp closures

5 a.m. Mon, Oct. 13 through 5 a.m. Wed, Nov. 5
Through 11 p.m. Fri, Nov. 14
5 a.m. Fri, April 18 through early November
9 p.m. Fri, April 25 through winter

Access changes

Mon, Oct. 27, 2025
  • Access to eastbound Co. Rd. 42 from southbound I-35W has permanently changed. Motorists will now use the newly constructed ramp at Buck Hill Rd. to access both eastbound Co. Rd. 42 and Buck Hill Rd.

Upcoming

Information about upcoming traffic impacts will be posted as details become available. Motorists can expect road, lane and ramp closures as work is completed.

Road closure

9 p.m. Wed, Nov. 11 through 5 a.m. Thu, Nov. 12
  • Northbound I-35W is closed between the I-35/I-35E/I-35W split and I-494
    • Detour: Northbound I-35 to northbound I-35E to northbound Hwy 77 to westbound I-494 to northbound I-35W

Ramp closure

Fri, Oct. 31 from 6 a.m. to 6:30 p.m.
  • The ramp from northbound I-35W to Burnsville Pkwy. is closed
    • Detour (eastside of I-35W): Northbound I-35W to eastbound Hwy 13 to southbound Nicollet Ave. to Burnsville Pkwy.
    • Detour (westside of I-35W): Northbound I-35W to Black Dog Rd. to southbound I-35W to westbound Hwy 13 to southbound Co. Rd. 5 to Burnsville Pkwy.

About this project

In coordination with the City of Burnsville and Dakota County, we will resurface I-35W between Cliff Rd. and the Burnsville Split.

Summary of work

  • Replace both pavement and concrete pavement on I-35W
  • Bridge repair, or replace bridges at Cliff Rd., Hwy 13 and Burnsville Pkwy.
  • Update guardrail
  • Improve drainage